If there is one thing that anyone that wants to build a home these days needs to know, it is that waiting is what you spend most of your time doing.
You wait for septic and well testing. You wait for survey, environmental, and engineering reports. Then design, design and revise designs to meet all restrictions and limitations. After that you start the permit process and the waiting really begins, here’s a list of some of the reasons (excuses) my permit process has been held up:
1. 2 month leave for maternity leave – ok but this was a dude!
2. 1 week – emergency appendix surgery
3. 1 week – sick days for common cold
4. 1 day each month county-wide furlough
5. 1 day each month federal holidays
6. 3 months lost to dispute needing to go before our hearing examiner. Then when we got before the hearing examiner, the county xlkserklja12!’s admited that they made a mistake and I was really correct all along.
These are just the excuses I got in person on occasion of personal visits to the permit office. This does not include all the days that are lost for no known reason, just no action, no communication, and no idea what is happening.
I submitted a plan in April of 2010, it is now August of 2011, I expect my permits to be issued any day now. But get this- its taken well over a year – and my plan and its details have not changed in any significant way.
Here is a picture of the Shack teau today, what a mess. And we wait……